Maryland Proton Treatment Center

Maryland Proton Treatment Center - May 2013

The Building:

Exp coating on the beamline of the new Maryland Proton Treatment CenterDuring the month of May, the spaces where the cyclotron, fixed beam and gantries will be located receive a lot of work. The walls were painted and the base coat of the epoxy floor was installed throughout. The maintenance platform where workers will be able to work on the proton therapy equipment was also installed in the gantry space. In the fixed beam space, the epoxy flooring was installed the piping and cooling towers were also put into place.

On the interior, all three floors received updates. On the first floor, the drywall and finishing was completed and an elevator and ambulance bay were put in place. On the second floor, drywall was also put into place. On the third floor, priority walls, overhead ductwork, plumbing, medical gas and fire protection substantially completed and were followed by installation of the balance of metal stud framing.

On the exterior of the building, the ground floor windows and roof flashing were substantially completed. Installation of the metal panel system at the curtainwall area and trellis continued throughout the month and the air and water testing of the window system also successfully completed.

Maryland Proton Treatment Center - April 2013

The Building:

Maryland Proton Treatment Center Construction Bunker RoofAt the spaces for the cyclotron and gantries, the walls were prepared, painted and the base coat of the epoxy floor was installed. The removable roofs were also constructed and set in this space. When the equipment is delivered, the roofs will be opened so the equipment can be lowered into the space (see photos of this process at the Scripps Proton Therapy Center in San Diego, CA). At the fixed beam rooms, walls were prepared and painted. Installation of the cooling towers and piping to service the spaces was done throughout the month. All this prep work paves the way for the future equipment arrival.

On the first floor, the main electrical room gear was installed and connected to be ready for power in May. Installation of the Varian and VIP/Ambulance elevators also began. On the second floor, overhead ductwork, plumbing and fire protection piping were completed. Design work began on the treatment corridor and recovery space. On the third floor, priority walls, overhead ductwork, plumbing, medical gas and fire protection were completed.

On the exterior of the building, the windows on the ground floor were installed. Roof detailing and flashing occurred as well as installation of the metal panel system at the curtainwall area and trellis began.

Maryland Proton Treatment Center - March 2013

During the month of March, the exterior of the building began to take shape with the brick and window installation.

The curtain wall installation at the Maryland Proton Treatment Center construction siteThe Building:

In the interior spaces, the team continues to make good progress. The installation of the primary gas and electrical services has begun as well as the installation of cable tray, conduit and piping. On the second and third floor of the Center, the team is working on overhead ductwork and pluming. The drywall is being installed on the first and second floors and will help the interior spaces take shape.

At the future site of the cyclotron, the team completed the topping slabs required for roof shielding thickness. At the third level, the balance of perimeter and interior walls thought out the power supply rooms were placed.  At the gantries, the installation of the cooling tower, related support steel and piping continued throughout the month.

In the steel building structure, the team built the steel over the concrete bunker where various staff offices will be in the future. Major mechanical equipment including chillers and related pumps along with the building fire pump were also installed.

On the exterior of the building, the windows, called the curtainwall system, continued to be installed on the southwest façade of the building. Roofing of the Center also began in March.

Maryland Proton Treatment Center - February 2013

The Site:

During the month of February site crews began replacing the permanent roadway removed earlier during construction. The installation of permanent gas and electrical service continued through the month.

Maryland Proton Treatment Center Construction Feb. 2013The Building: Concrete Structure:

In the concrete structure, mechanical and electrical the team continues installing cable tray, conduit and piping. At the cyclotron, the team placed topping slabs to make up the rest of the roof shielding thickness. Walls at the third level perimeter and interior walls of the cyclotron electrical room and related rooms were placed. Also, shoring throughout the cyclotron area was removed and concrete rub and patch will occur followed by painting.

At the gantries, the team formed and placed the filler slabs which make up the shielding thickness at the labyrinth and beam transport system areas. The bearing wall which supports the balance of the third floor structural steel was placed. Concurrently, the walls which make up the last layer of the Gantry 1 through 4 walls were placed.

At the fixed beam, formwork and rough in was completed at the roof slab. It was followed by placement of topping slabs which make up the balance of the shielding thickness. The shear walls which make up the northeast corner of the structural steel building continued to be placed throughout February allowing the balance of precast to be erected in mid-March.

The Building: Steel Structure:

Steel crews continue decking the third floor and roof over the retail spaces as well as the trellis steel on the southwest corner of the building. They will also erect and deck the third floor steel over the concrete bunker where various staff offices and toilets will be. Metal stud framing, plumbing and mechanical system piping, as well as electrical conduits, were installed on the first and second floors.The glazer continued building of the curtain wall system at the southwest façade of the building. Drywall crews worked with the glazer to frame the exterior column wraps that interface with the curtain wall. Windows on the north and west elevations were installed in precast.

On the interior, drywall crews continued framing priority walls at the south end of level 1 and throughout level 2 and will begin to frame/hang stair and elevator shaft walls. The mechanical and plumbing teams continued hanging overhead pipe, duct work on level one and begin hanging on level two.

Maryland Proton Treatment Center - January 2013

January was a pivotal month in the construction of the Center with the topping out of the building.

Maryland Proton Treatment Center Topping Out Jan 2013The Building: Steel Structure

The Center celebrated its “topping out” with a ceremony at the building site on January 17, 2013. Topping out is a major construction milestone, marking the last steel beam being laid in the building. Advanced Particle Therapy celebrated the milestone with The University of Maryland School of Medicine and its Department of Radiation Oncology, which will operate the proton therapy center and Haskell, the architecture, construction and engineering firm for the project, in celebrating this milestone with a traditional topping out ceremony. The facility is scheduled to begin treating patients in 2015.

For a complete account of the Ceremony, please visit the press room.

 

After completing the steel building structure, the complete decks were placed on levels two and three. Precast will start early in the month on the north face of the building. The glazer will also be onsite to start layout and install of the curtain wall system at the southwest façade of the building.

Drywall crews will work with the glazer to frame the exterior column wraps that interface with the curtain wall. On the interior, drywall crews started framing priority walls and setting door frames. The mechanical and plumbing trades hung overhead pipe on level one and the electricians started running conduit and wiring for mechanical piping on the first floor as well.

The Building: Concrete Structure

In the cyclotron space, the trench embeds began and ran remaining conduits prior to placing the beam transport tunnel topping slab. Shoring was set and forms placed to pour the elevated slab for storage and cyclotron electrical room.

At the gantries, the team formed and placed the labyrinth and ring walls from gantry 1 through 4 at the second floor level. The beam transport system trench topping slab was placed and crews began shoring and forming up the roof of the beam transport system tunnel and labyrinth roofs.

At the fixed beam room space, the east exterior wall of the beam transport system tunnel and the north exterior wall were places. The labyrinth walls were formed, conduits ran and concrete placed. Concrete was also placed for the north exterior wall near the fixed beam control room. 

Pages