Emory Proton Therapy Center

Emory Proton Therapy Center - February 2014 Update

Aerial view of the Emory CenterProgress on the Emory Proton Therapy Center continued at a breakneck pace in February, even through the snowstorms that hit Atlanta. With the major concrete work done, Brasfield & Gorrie (B&G) was able to turn to the installing the steel frame of the rest of the main clinical building.  This work happened quickly, with the majority of the building’s three stories worth of steel beam being put in place.  The building is starting to resemble what will be its final proportions.  

At the same time, B&G worked inside the concrete spaces to clean, prep, and seal the concrete walls.  A walk through this space shows much of this work underway, and even some of the piping being installed.  In order for Varian to bring in the proton therapy equipment, these spaces must be all clean, dust free, and conditioned. March will see this work continue, and will see some of the major mechanical equipment, like chillers, begin to arrive at the project site.

To date more than 400 requests for information have been posed by the construction team, and all have been answered quickly by the design team.  This is critical, as each RFI helps keep the quality high, and ensure that future delays and added cost can be avoided.  We are quickly progressing through the exciting phase of major construction that shows change almost daily in the project.  The project continues to be well received by our neighbors in Atlanta, as well, with excitement for the center continuing to mount within the community.

Emory Proton Therapy Center - Jan 2014 Update

Emory Proton Therapy Center Construction Photo January 2014January saw the completion of the concrete for the proton portion of the Emory Proton Therapy Center.   Brasfield & Gorrie finished this on January 27, 2014. To date more than 26,000 cubic yards of concrete has been poured on this project, just under 80% of the total needed for the entire building. 

This clears the way for the construction of the steel portion of the building to begin.   With the extreme cold weather moving through Atlanta, the team has had to delay for a few days, but expects to start putting up steel within the week. This work should last about 6-8 weeks.  

During this time, the concrete bunker that was constructed for the proton therapy equipment will be prepared for the arrival of the Varian proton equipment. The building must be clean and dry and temperature and humidity controlled to allow for that equipment to be safely installed.  

The entire project team continues to excel and work well together, with almost 400 requests for information processed, all on time. The teamwork and professionalism on display daily at the project is a great indicator of the future success of the project, and we are proud to be bringing this to the metro Atlanta area.

Emory Proton Therapy Center - Dec 2013 Update

Emory Proton Therapy Center Construction December 2013December was a good month for the Emory Proton Treatment Center project. A lot of progress was made in the concrete construction of the building. The proton therapy system section concrete pour is quickly nearing completion, with the roof section of the northern two gantry treatment rooms currently being poured. The roof sections of the southern two gantry rooms will follow, and we expect this portion of the concrete work to be done in only a few months. 

The concrete poured to date represents more than 70% of the almost 34,000 cubic yards that will be used on the project in total. This also represents the culmination of some amazing design and engineering, as well as construction efforts. 

The construction continues to track ahead of schedule.  By early February, it is anticipated that the steel building will begin construction. This will be a fascination display of acrobatics as the project’s two tower cranes will need to maneuver the large steel beams into position. Keep an eye on our web cam to see this in action

In addition to constructing a world-class cancer treatment facility, the team was proud to give more than 200 presents to Toys for Tots over the holidays to help local families enjoy their holidays a little more.  We are proud to be making such a positive impact in Atlanta in more ways than one.

Emory Proton Therapy Center - November 2013

The construction continues at the jobsite with excellent progress along the proton therapy treatment wing.

Brasfield & Gorrie continued to make fast progress on the concrete construction of the Emory Proton Treatment Center.  Vertical concrete construction continued moving down the length of the building, north to south.   The vertical walls of the other gantries are almost complete, and the treatment structure is quickly taking form.  To date, 66% of the total concrete for the job has been placed.  

Brasfield and Gorrie Donates Toys for Tots at the Emory Proton Therapy Center December 2013The next major step will be to create the roof pieces over the gantry treatment rooms and some support spaces.  Foundation work has also made fast progress, preparing for the steel portion of the structure to begin. 

In addition to keeping pace on the promised construction schedule, the project team has also taken time to help the community, with Tony Burgess, the Senior Project Manager, organizing a toy drive to support the local chapter of Toys for Tots.   The project team stepped up and pulled together a great assortment of toys that are sure to make a lot of kids happy this holiday season.

Emory Proton Therapy Center - October 2013

October saw a lot of progress be made on the concrete portion of the Emory Proton Treatment Center.   Almost all of the vertical walls on the north half of the building have been poured, including the fixed beam room and two of the gantries. The roof has been poured on top of the fixed beam room, as well.  

Work has also been done to define and finish what will be the maze entrances to each treatment room, and the cyclotron. The concrete portion of the building is starting to look much more closely like what it will when finished. Foundation work for the steel clinical building that will be married to the concrete building has begun. This portion of the facility goes up much more quickly than the concrete portion. 

Varian continues to be on site frequently, as do the building design and engineering teams, to help answer questions and keep the project moving forward and on schedule.  

To date, the project has created 210 of a projected 1,000 jobs, and continues to be a project of great interest throughout metro Atlanta.

Pages